Waldorf Astoria Hotel Millwork
Project N819 ยท CAS - New York
Financial summary
- Adjusted contract amount
- $8,751,689
- Costs to date
- $5,638,679
- 64.4% of adjusted contract
- Billed to date
- $8,751,689
- Payments received
- $8,751,689
Project details
- Project number
- N819
- Project manager
- Alex Saharig
- Project date
- Dec 15, 2022
- Original contract amount
- $8,100,000
Contractor and contact
- General contractor
- Suffolk Construction
- Contact
- Kevin Mangan
- Phone
- (646) 879-5682
- Address
- One Pennsylvania Ave, New York, NY 10119
Cost and billing details
- Subcontract costs not in books
- $0
- Open purchase orders
- $0
- Total project costs
- $5,638,679
- Pending change orders
- $0
- Extra work orders
- $606,053
- Proposals
- $99,766
- Overhead G&A
- $875,172
- Last entry
- Oct 16, 2026
Illustrative data. COR images are not included in this sample.
Hours and reporting
- Budget hours
- 78,379
- Actual hours
- 48,585
- Completion
- 96%