Compare project hours and completion

Remaining baseline hours = equated hours − actual hours. Negative values exceed this illustrative baseline.

Illustrative project hours and completion
ProjectBudget hoursEquated hoursActual hoursRemaining baseline hoursDays elapsedCompleteLast update
Waldorf Astoria Hotel MillworkProject N819 78,37975,73848,585 27,153 658
96%
May 28, 2025
JFK New T1 RedevelopmentProject N822 330,941308,900306,590 2,310 755
92%
Oct 16, 2026
80 ClarksonProject N824 239,714201,703215,926 Over baseline: (14,223) 572
83%
Oct 15, 2026
TSRC Hotel EvolutionProject N825 86,51270,96366,276 4,687 441
81%
Mar 6, 2026
Mary Cali Dalton CenterProject N828 18,1499,09510,872 Over baseline: (1,777) 230
50%
Apr 7, 2026
NYPA HQ Building Core & ShellProject N830 20,39014,22014,173 47 233
69%
Sep 11, 2026
383 Madison Temp ProtectionProject N831 104,64545,11831,785 13,333 292
43%
Sep 25, 2026
USTA Player Performance CP-02Project N832 52,9856,8806,451 429 162
12%
Sep 24, 2026