XPress
Compare project hours and completion
Remaining baseline hours = equated hours − actual hours. Negative values exceed this illustrative baseline.
| Project | Budget hours | Equated hours | Actual hours | Remaining baseline hours | Days elapsed | Complete | Last update |
|---|---|---|---|---|---|---|---|
| Waldorf Astoria Hotel MillworkProject N819 | 78,379 | 75,738 | 48,585 | 27,153 | 658 | 96% |
May 28, 2025 |
| JFK New T1 RedevelopmentProject N822 | 330,941 | 308,900 | 306,590 | 2,310 | 755 | 92% |
Oct 16, 2026 |
| 80 ClarksonProject N824 | 239,714 | 201,703 | 215,926 | Over baseline: (14,223) | 572 | 83% |
Oct 15, 2026 |
| TSRC Hotel EvolutionProject N825 | 86,512 | 70,963 | 66,276 | 4,687 | 441 | 81% |
Mar 6, 2026 |
| One Pace East RenovationProject N826 | 49,997 | 49,552 | 55,774 | Over baseline: (6,222) | 492 | 100% |
Jul 16, 2026 |
| Sofitel NY RenovationProject N827 | 18,483 | 12,620 | 10,229 | 2,391 | 205 | 63% |
May 27, 2025 |
| Mary Cali Dalton CenterProject N828 | 18,149 | 9,095 | 10,872 | Over baseline: (1,777) | 230 | 50% |
Apr 7, 2026 |
| NYPA HQ Building Core & ShellProject N830 | 20,390 | 14,220 | 14,173 | 47 | 233 | 69% |
Sep 11, 2026 |
| 383 Madison Temp ProtectionProject N831 | 104,645 | 45,118 | 31,785 | 13,333 | 292 | 43% |
Sep 25, 2026 |
| USTA Player Performance CP-02Project N832 | 52,985 | 6,880 | 6,451 | 429 | 162 | 12% |
Sep 24, 2026 |