Art Chart
N819 · Work package hours and installation progress
Work package hours
N819 · Sample actual vs budget hours
Installation progress
Partitions
92%
Millwork
85%
Ceilings
78%
Finishes
45%
Completion percentage is illustrative and does not imply productivity or risk by itself.
Work package data
| Work package | Budget hours | Actual hours | Complete |
|---|---|---|---|
| Partitions | 12,000 | 10,800 | 92% |
| Millwork | 18,000 | 16,100 | 85% |
| Ceilings | 9,500 | 8,200 | 78% |
| Finishes | 17,000 | 13,485 | 45% |