N819 · Work package hours and installation progress

Work package hours

N819 · Sample actual vs budget hours

Installation progress

Partitions 92%
Millwork 85%
Ceilings 78%
Finishes 45%

Completion percentage is illustrative and does not imply productivity or risk by itself.

Work package data

Sample work package hours
Work package Budget hours Actual hours Complete
Partitions 12,000 10,800 92%
Millwork 18,000 16,100 85%
Ceilings 9,500 8,200 78%
Finishes 17,000 13,485 45%